2005.03.17
Texas DOT March 11
signed a so-called Comprehensive Development
Agreement (CDA) or contract with
Cintra Zachry LP
(CZ) purporting to develop some 508km (316mi) of tollroad between Dallas and San Antonio in the Trans
Texas Corridor 35 (TTC35). Despite its length (348
pages) and its name the agreement is not at all
comprehensive. It says nothing at all about the
developer's right to collect tolls, how toll rates
will be set, or the term of any toll concession. The
agreement commits the developer only to some 15
months and $3.5m worth of planning and study work
working to the department, not even to any detailed
design, not to any financing, nor to building, nor
to operating anything. $3.5m doesn't go very far
even in studies and planning these days. Many road
projects much less ambitious than TTC35 go to $20m
in planning and studies before any detailed design
occurs.
There is a huge gulf
between the overwrought rhetoric that accompanied
the signing of this contract and the actual words of
the document. This most noncomprehensive agreement
which should be named a Planning Agreement merely
lays out a process to bring the project in segments
to the stage where they can be considered by TxDOT.
No process is laid down for what happens next, if
anything.
A press release notes
that the developer CZ "is proposing to invest $7.2b
to help build TTC35." Most of the news coverage
echoed that but reporters cannot have read the 103
pages of the main contract and 245 pages of annexes.
We have. It is long on lawyerly backside protection
for every conceivable contingency and short on
substance. It commits CZ to not one cent of
investment. The $7.2b figure doesn't appear in the
agreement. Nor does it grant
CZ any rights to build
or operate TTC-35, just to do some work for TxDOT to
bring the projects to the stage where they are
defined and studied, so TxDOT can decide what, if
anything, happens next. As compared to the $7.2b
mentioned in the hype, planning work worth a mere
$3.5m is actually authorized.
The press statement
quotes Ric Williamson chairman of the Texas
Transportation Commission, the state's governing
body for policy as stating: "This partnership brings
private investment - billions of dollars in private
investment - to provide congestion relief to I-35.
Private sector funding will help put transportation
improvements on the ground sooner."
The agreement just
signed however doesn't provide for, or commit, any
private investment, let alone "billions."
It remains true that
TxDOT has accepted in principle the
CZ proposal to
spend $7.2b, $6b of which would be used for the
Dallas San Antonio tollroad, and $1.2b as a tolling
'concession fee' which would be used by TxDOT to
fund other rail or road improvements in the
corridor. But that remains an acceptance in
principle only. The so-called comprehensive
agreement mentions none of it. The agreement just
provides for the writing of a master development
plan and a master financial plan, the necessary
preliminaries to be sure, but no more.
Termination for
convenience
Even this modest
commitment to planning can be terminated by TxDOT at
any time: "Termination for convenience 20.1 TxDOT
Right to Terminate TxDOT may at any time, in its
sole discretion, terminate this Agreement, in its
entirety or as to a specific Facility or Facilities
(a partial termination for convenience), when TxDOT
determines that such termination is in the best
interests of the State."
It does provide for the
developer to get compensation.
The development plan
will include:
-
a list of specific
transportation facilities that could be
developed in the near-term (2005-2010), mid-term
(2010-2025) and long-term (after 2025).
-
an overall project
schedule describing implementation of the
specific facilities, subject to federal
environmental approval.
-
a master financial
plan.
-
identification of
facilities Cintra-Zachry would like to develop
itself (called 'self-performance') - still
requiring negotiation with TxDOT
Each facility identified
in the master plan is to include:
-
a conceptual design,
including requirements for support services such
as rest stops and maintenance yards.
-
preliminary traffic
and revenue studies.
-
preliminary cost
estimates, as well as the sources of funds
required for development and operation.
-
identification of
existing and planned transportation projects
that could impact the potential facility.
-
a plan for complying
with mitigation and environmental requirements
of permits and other necessary approvals.
-
identification of
potential third party agreements and approvals
that will be needed to develop the facility.
Alignments will be
established only toward the end of the process.
Individual parts of the
project will be dealt with by what are called
Facility Implementation plans. If TxDOT approves the
request, the developer will finalize the facility
implementation plan. This will include a detailed
budget and project schedule, responsibilities of all
parties, and other necessary work needed to bring
the proposed project to a financial closing and
potential construction in the future. If the
implementation plan is approved, TxDOT will enter
into a Facility Agreement authorizing the developer
to proceed with the work. But significantly
CZ
doesn't have any special right to develop the
facilities. TxDOT has the option to seek competitive
bids for facility agreements from other developers.
Provision for
traditional financing or toll concession at TxDOT
discretion
Three different
approaches may be taken by TxDOT:
(1) traditional design
first, bids for construction, with traditional
government funding
(2) design-build with
traditional government funding
(3)
design-build-operate-maintain with a toll concession
Inside run on $400m
guaranteed
The only inside edge for
CZ is that during the planning work one or more
near-term projects with a cost of $400m or more will
be identified and approved by TxDOT for
'self-performance' by CZ - a right of first
negotiation.
Although this agreement
gives the developer no rights to actually do
anything it lays out some requirements for when such
rights are granted:
-
TxDOT will hold
title to all right of way, structures, pavement
and other improvements granting leasehold rights
to CZ.
-
CZ will have to
abide by all state and federal disadvantaged and
minority business provisions
-
All
CZ employees
have to have licenses and skills deemed
necessary by TxDOT which has the right to have
them removed
-
TxDOT will have the
right to vet senior appointments
-
Key
CZ employees
have to be contactable 24 hours/day, 7 days/week
(during planning and studies?!?)
-
during development
CZ employees must be co-located with TxDOT
insurance levels are set
by TxDOT
PPP definition
There's an interesting
lawyerly definition of what a 'public private
partnership' is and isn't: "This Agreement does not
establish, and shall not be construed as, a legal
partnership between TxDOT and the Developer. Rather,
by 'public private partnership,' the parties intend
and acknowledge that a highly cooperative, mutual
collaboration will be pursued, under the terms of
the Contract Documents, to engage the Developer's
innovation, private sector resources,
entrepreneurial skills, risk sharing and management
capabilities, and technical and financial expertise,
and to engage TxDOT's governmental authority,
planning capabilities, risk sharing and management
capabilities, and technical and financial expertise,
to bring the Project and Facilities to fruition. As
such, this Agreement contemplates significant roles
and responsibilities for the Developer that go
beyond the typical work and services provided by
engineering and construction firms under contracts
routinely let by TxDOT." (p6)
Standards
There are some
interesting small variations from usual standards in
the truck facilities:
-
3.96m (13ft) main
lanes
-
4.27m (14ft) lanes
on ramps
-
5.03m (16.5ft)
overhead clearance under bridges
-
129km/hr (80mph)
design speed
-
HS25/Military
Alternate bridge loading standard - 25% greater
than the more usual HS20 for interstates but a
standard already used by many turnpikes, and no
distinction between truck and car roadways
There is no departure
from normal interstate standards in pavement
construction.
Toll collection must be
at least present standards of "open road tolling/all
electronic implementation."
A detailed dispute
resolution procedure is laid down.
All state and federal
requirements have to be followed whether or not
there is state or federal money for a facility -
including "goals" for minority hiring and union pay
scales.
The
CZ team is 85%
Cintra and 15%
Zachry, a major Texas construction
firm which is also active in building US embassies
in several countries. Another 16 companies are
enlisted as partners.
TOLLROADSnews 2005-03-16