C-Town Raceway

Work begins!  The area had been rough-graded months earlier and the contractor had to move very little dirt for the flatwork.  This photograph is looking south towards a half-court basketball court.  There had been about four-weeks required for David to complete all the construction plans in his spare time.  It took another two-weeks to bid the work.  Then there was an unexpected six-week delay on the part of the contractor. 

(09.17.02)