Costs, delays
with 281 argued
09/15/2007
Patrick Driscoll,
Express-News
One of the biggest blame games in the muddy
debate over toll roads involves jaw-dropping
escalations in costs to widen U.S. 281 and years
of frustrating delays to start construction.
Work actually did start in late 2005, but it
was two years behind schedule, and all that
crews managed to do before having to stop was
snap some live oaks and scrape them into piles.
As noise continues to mount on whether to
build an 8-mile tollway from Loop 1604 to Comal
County or go with just three miles of freeway
and a non-toll overpass at Borgfeld Road, costs
soar in double digits annually and accusations
fly over the holdups.
When Texas Department of Transportation
officials outlined a plan in 2001 to rebuild
eight miles of U.S. 281 into a freeway and add
long-awaited ramps directly linking the highway
to Loop 1604, they figured it would cost $263
million.
But they could only afford three miles, from
Loop 1604 to Stone Oak Parkway, and the bridge
at Borgfeld.
So to raise cash for all eight miles and then
some, the freeway plan was converted several
years later to a tollway plan — tolled express
lanes with free frontage roads. Critics followed
with a lawsuit to force more study of the
environmental impacts, halting the work in
January 2006.
Then last month, as the Federal Highway
Administration announced a finding of no major
impacts, allowing the project to proceed, TxDOT
dropped a bombshell: The tollway will now cost
$675 million.
The stunning difference is enough to strike
fear in motorists weary of worsening slogs on
the highway and to stoke desperation in those
fighting the freeway versus tollway battle.
"Simply unbelievable," said state Rep. Nathan
Macias, R-Bulverde, who called for TxDOT to
revert to the freeway plan. "Attempts to overrun
the citizens with numbers games is the oldest
trick in the book."
TxDOT explains
TxDOT officials insist that they're not playing
around and can explain. The costs didn't go up
as fast as critics claim, they say, but there's
still cause for alarm.
Part of the problem is that the estimates for
2007 and 2001 aren't comparable. The latest
number includes $85 million for studies and
engineering and $120 million for land that
wasn't part of the 2001 figure.
That leaves $470 million for construction, an
apple-to-apple cost that's still a whopping $207
million, or 79 percent, higher than six years
ago.
And that's what's scary, TxDOT officials say.
Highway construction costs in Texas have shot up
73 percent in the past five years — much faster
than consumer inflation — because of spiraling
fuel prices and intense global competition for
asphalt, concrete and steel.
"The longer we wait to build it, the more
costs will go up," said David Casteel, TxDOT's
lead engineer in its San Antonio office. "It is
not a conspiracy, it is just inflation in the
construction market."
A low bid in 2005 to start the first three
miles of U.S. 281 even outstripped statewide
construction inflation. The $78 million offer
was $19 million more than forecast.
"The free market ruled," Casteel said of the
unexpected bump in cost. "The 2, 3 and 4 bidders
were much higher."
The free market is still having a say on
costs for the three-mile project, which could
have been 70 percent complete if Aquifer
Guardians in Urban Areas and People for
Efficient Transportation hadn't filed a lawsuit
to demand a detailed study of tolling and
pollution impacts.
Estimated costs have since gone up another
$20 million.
"The delay caused by the legal challenge made
it tougher to provide mobility and improve
safety for the public," TxDOT engineer Frank
Holzmann said. "What a shame and what a waste of
tax money."
Bait and switch?
Critics charge that TxDOT pulled a bait and
switch years before, dangling funds and then
stalling to switch to a toll plan and let
burgeoning traffic bring motorists to their
knees.
"They know what they're doing," Bexar County
Commissioner Lyle Larson said. "They wanted to
get it into an untenable situation where people
say, 'Well, just do something.'"
As a board member of the Metropolitan
Planning Organization, which oversees spending
of federal gas taxes in San Antonio, Larson
helped line up funds in 1999 for several bridges
to bypass U.S. 281 traffic lights. In 2001,
money was earmarked for the three miles of
freeway lanes.
TxDOT, with two engineers on the MPO board,
was scheduled to start work on the bridges in
2002 and the freeway the next year. But by early
2003, the agency was studying which projects
statewide could be financed with tolls, and U.S.
281 emerged as a hot prospect.
"We would have had those overpasses built by
the end of 2004," Larson said. "This is long
before the lawsuit."
Rising with aggravation was the price. By the
time TxDOT was ready to start construction, the
expressway and its interchange at Stone Oak
Parkway went from $48 million in 2003 to $78
million just two years later, a jump of 63
percent.
The cost today is $100 million, up another 28
percent because of the lawsuit.
TxDOT says the financial and environmental
studies needed to turn the freeway into a
tollway didn't slow anything down.
"We bought the last piece of property in
2005, so we couldn't have gone to contract any
sooner than that," TxDOT engineer Julie Brown
said.
Freeway or tollway?
Critics are fuming and say some of the nearly
$300 million in gas taxes and other public funds
that the MPO has set aside through January 2011
to subsidize toll lanes on U.S. 281 and Loop
1604 should be used to refund the original U.S.
281 freeway and overpass plan.
"Why should anyone have to pay a toll when
they have the plan, the clearance and the money
to fix U.S. 281 as a freeway?" said Terri Hall
of San Antonio Toll Party. "There is no
justification other than greed and to tap the
vein of 281 users to fund other road projects."
Casteel, in charge of TxDOT's San Antonio
office since 2003, said money would have to be
taken from other projects or raised some other
way to add non-toll lanes to U.S. 281. With toll
lanes, funds could be borrowed and repaid from
tolls.
"I really don't know what she could be
talking about as far as a funded expressway
project, because there's not one," Casteel said.
"If people could figure that out, that's a good
thing. I don't know how to do that."